Water and Sewerage System -R.Inguraidhoo

01 September 2021

Water and Sewerage System -R.Inguraidhoo
Water and sewerage project completed. The testing/commissioning of the facilities were conducted from 30 June - 02 July 2022. The project is implemented as per the Integrated Water Resources Management (IWRM) approach by incorporating Rainwater harvesting into the RO system and by integrating solar energy, a reliable green energy solution.  
  • Share:

Is completed

100 Percent

Inauguration Date

29 September 2019

Duration

681 Days

Deadline: 10 August 2021

Latest Update Date

18 July 2022

Project Value

33,995,525 Ruffiyaa

Assigned Vendor

Altek Maldives Private Limited

Status

COMPLETED