Harbor dredging works on going
02 September 2021
Is completed
37 Percent
Inauguration Date
24 September 2019
Duration
774 Days
Deadline: 06 November 2021Latest Update Date
02 September 2021
Project Value
57,124,555 Ruffiyaa
Assigned Vendor
Maldives Transport and Contracting Company
Status
ONGOING